Get Ready To Celebrate – The Building Projects Are Almost Complete

WE are almost there As you watch our latest drone video, you will see the great progress that has been made.  And know that it will look even better when you come to church this Sunday with the completion of landscaping and new exterior paint on the exterior of the Fellowship Hall wing.  Final inspections are in process for the majority of the project and we are almost ready to celebrate.  But first, take a look at where we were…

What A Mess It Is Now – What A Blessing It Will Be

As we rapidly move toward the completion of our Embrace and Transform Building Project, things at the church are an absolute mess!  Other than the interior of our sanctuary, gym and New Children’s Center, every other area of the facility is or will be under construction or renovation during the next few weeks.  We appreciate the patience of all of our members and visitors during this time of transition.  The good news is that we are almost there and will…

Entering the Home Stretch

Children’s Center – Opening Celebration – Sunday June 2nd Our current plan is to hold our first Sunday morning children’s classes in the new Children’s Center on Sunday, May 26th.  For now, we will continue to utilize the current check-in system with the new electronic system planned for later this summer.  Please plan to join us for the Children’s Center Opening Celebration on Sunday, June 2nd. Hospitality atrium Sneak Peek – Sunday May 26th On Sunday, May 26th, you will…

Construction Is Progressing Rapidly

We continue to make great progress on the construction of our new Children’s Center and Hospitality Atrium.  To see the latest, watch the video below. Children’s Center We now anticipate that our Children’s Center will be open before Memorial Day!  We’ll have a special “sneak peek” tour on Sunday morning, April 28, to get an inside look at the new facility. Stayed tuned for more information to be shared during worship on Palm Sunday, April 14. HOSPITALITY ATRIUM AND COURTYARD…

Hospitality Foundation Poured – Steel Assembly Almost Complete

Hospitality Space Last week, our construction crew poured the foundation for the new Hospitality Atrium.  You can see that area in the picture below.  The pipes coming through the slab to the left will provide the plumbing for our new coffee bar. As you can see below in this week’s “View from Above,”  the steel assembly has progressed quickly.  Watch closely starting at :52 seconds, and you will see the beam that the congregation signed and added their prayers back…

Construction Progress Continues

Children’s Center Update This has been a great week for the construction team as the roof has been installed on the Children’s Center and we are finally dried in.  The back-end HVAC, plumbing, and electrical work are almost complete, and the drywall will begin to be installed in the next few days.  Some Building Committee members took our Children’s Ministry Director, Mary Freeman and Children’s Ministry Assistant, Trish Morehead, on an interior tour yesterday. As you can see below, they…

Children’s Center Taking Shape

Children’s Center Update Since the arrival of the steel a few weeks ago, the contractors have made great progress creating the shell for the new Children’s Center.  As you can see below, the roof deck is on, the interior wall framing is up, and the HVAC ductwork is in process.  We should be dried in completely within a couple of weeks and then moving forward with the interior work. Many of you became a part of our new atrium At…

Onward and Upward

A View from above The Steel Has Arrived On January 9, the steel arrived for our building project, and our workers have begun assembling our Children’s Center.  We expect the steel framework and deck for the Children’s Center to be complete in approximately two weeks. BEAM SIGNING THIS SUNDAY: PUT YOUR NAME ON OUR NEW ATRIUM We have placed a steel beam for our new atrium has been placed outside our east entrance. On Sunday, January 13, after worship, we…

Making It Concrete

Rain, Rain Go Away So We Can Pour Some Concrete Today! Have you noticed, we have had a lot of rain this fall?  Our contractors are painfully aware as it has affected our construction schedule almost every week.  But they have patiently persevered, and today, they were able to pour the slab for the new Children’s Center.  As you can see in the pictures and video below, Pastor Todd was on hand, making sure that your prayers, collected in worship…

Our New Facilities Will Begin to Take Shape in December

Concrete Slab Work to Begin in Early December After 3 months of demolition, excavation and site preparation, the actual new construction of our new Children’s and Hospitality Additions will begin next week.  During December, the concrete slabs for both facilities will be poured followed by the assembly of the structural steel which will support both facilities.  Please be cautious as you enter and exit the facilities, especially during weekdays as there will be many trucks entering and exiting our property.…

As the Concrete Work Begins, Your Prayers Help Build the Foundation

Site preparation underway for Concrete pours Now that the former Youth Building demolition is complete, our contractors are preparing the site to pour the concrete foundation for our new Children’s Center and Hospitality Atrium.  Part of this preparation involves the underground plumbing, sewer, and storm drain work needed for the facility changes. Then, they’ll regrade the areas and test for moisture.  Once these tasks are complete, the contractor will pour the new concrete piers and grade beams in preparation for…

Access Changes, Stained Glass Removal, and Schedule Updates

Demolition Almost Complete in Spite of Difficult Conditions Did you notice that we have had a little rain in October?  In spite of these difficult conditions, the construction crews continued toward the finish line to complete the demolition of the former Youth Center and to finish site preparation for the construction of our new Children’s Building. Here are some video updates of the work completed this week: Access changed to east parking lot Effective immediately, we will no longer be…